Construction Update: Hancock Street Mill and Pave

Construction Update


PROJECT NAME: Hancock Street- Mill and Pave

PROJECT LOCATION: Hancock Street from Rt. 13 to Third Street

PROJECT START DATE: Monday, July 9, 2018

PROJECT DESCRIPTION AND GOAL: Remove old asphalt and pave binder the first week. Set manholes and pave the second week.

LOCAL IMPACTS: Street Closed, no through traffic, only residents and businesses.

RECOMMENDED DETOURS IN PLACE: No detour at this time.

SCHEDULED COMPLETION DATE: July 20, 2018.

For additional information and questions please contact Cliff Murphy, Supervisor of Streets, at cmurphy@cityofithaca.org or (607) 272- 1718.