Construction Update- Warren Place Culvert Replacement


PROJECT NAME:   Warren Place Culvert Replacement

PROJECT LOCATION 300 block of Warren Place 

PROJECT START DATE:  September 24, 2018

PROJECT DESCRIPTION AND GOAL: Relocate utilities, replace pipe and headwalls.

LOCAL IMPACTS:  Complete closure, no on-street parking.  Access will be from either North or South of excavation

RECOMMENDED OR STATE DETOURS IN PLACE:   Cliff Park Rd to Richards Pl. to Warren Place

SCHEDULED COMPLETION DATE:   December 7, 2018

Please note, construction, by nature, is subject to constant change, inclement weather, and unexpected findings.

For additional information please contact Cliff Murphy, Supervisor of Streets (607) 272-1718 cmurphy@cityofithaca.org

 