Construction Update- Six Mile Creek

Construction Update- Six Mile Creek

PROJECT NAME: Raw Water Line Stabilization Project

PROJECT LOCATION: Raw water line along Six Mile Creek

WORK DESCRIPTION:  A contractor for the City will be stabilizing the raw water pipe that runs near Six Mile Creek at two locations. In the first location, rock anchors and a pipe support will be installed.  At the second location, an existing concrete sluiceway and concrete pipe supports will be replaced. 

PROJECT START DATE: Mobilization to begin on Tuesday, July 30th

SCHEDULED COMPLETION DATE: Final completion scheduled for October 2019

LOCAL IMPACTS: Construction vehicles and equipment will be using the access road/trail off of Giles St to reach the construction sites. Pedestrian access will be restricted around the construction areas but maintained as much as possible along the access road/trail.

For additional information contact: Matt Sledjeski, Scott Gibson, or Erik Whitney, DPW, Water & Sewer Division  (607) 272-1717  

Raw Water Main Stabilization Project Work Areas