News Flash

City of Ithaca News

Posted on: January 31, 2024

Construction Update: Cook Street

Work Zone

Construction Update: Cook Street
 

PROJECT NAME & LOCATION: Storm Pipe and adjoining Catch Basin installation, Cook Street between Eddy St & Blair St.

PROJECT START DATE: Monday, February 5, 2024

PROJECT DESCRIPTION AND GOAL: - Install Storm Pipes & Catch Basins

LOCAL IMPACTS: The indicated road will be temporarily closed during Storm Pipe Installation from February 5, 2024, through March 22, 2024, between the hours of 7am – 3:30pm. Sidewalks will not be affected by this construction.

Emergency vehicles and local residents will have access to driveways though-out the duration of the project. Some parking will be accessible. Parking near the work zone will be utilized for city vehicles and will be posted. Some delays should be expected during work contingent on winter storms. The street will remain closed for the duration of the project.

RECOMMENDED DETOURS: None currently

ESTIMATED TIME FRAME: 46 days

SCHEDULED COMPLETION DATE: Friday, March 22, 2024

PLEASE NOTE: Construction, by nature, is subject to constant change, inclement weather, and unexpected findings.

FOR ADDITIONAL INFORMATION CONTACT: Hank Bennett (607) 272-1718 ext. 4231; hbennett@cityofithaca.org

Facebook Twitter Email